In August 2015, ContourGlobal Hydro Cascade CJSC acquired “Vorotan Complex of Hydroelectric Power Stations CJSC” in Syunik region in the south of Armenia. Refurbishment of the three Hydropower Plants Tatev, Shamb and Spandaryan was planned in order to ensure grid stability and frequency control throughout the year.
In a first step, GefaÖ assessed all power plants and water reservoirs regarding existing health, safety and environmental risks. Based on this, an Environmental and Social Impact Assessment (ESIA) Report and the corresponding management plans for the rehabilitation of the power plants were prepared by GefaÖ in 2017. Other services provided by GefaÖ included stakeholder and public consultations, as well as monitoring the implementation of the ESMP through quarterly site visits in 2018-2021.